Monday 19 April 2021

Progress on Phase 2 of Stillwoods Lane

 

Frizzle road
Progress on Phase 2 of








Stillwoods Lane.

19 April 2021.

Stonesage, and Reg MacKinnon have been working on the extension of Stillwoods Lane.

At this time there are two limitations.

Frizzle road (left) and Stillwoods Lane (Southwards)

There is an intermittent stream that crosses lot 5 (phase1). The culvert for this crossing cannot be installed in the Springtime.

The other limitation is the Spring Axle Restrictions which limits loads that can be transported. I believe it is in effect still.

These photos are from today! Just after a big rainstorm, Saturday and Sunday.

Stillwoods Lane (Northwards)

They show Stillwoods Lane, work in progress, and Frizzle road---a temporary access so that the stream is not being crossed. ‘Frizzle road’ will become a pathway on the completion of Stillwoods Lane extension.

An update on the surveyors---they have been in and out. The work is still very incomplete.

Because the survey is incomplete, there can be no submission to HRM for Final Approval of phase 2.

Hopefully things take shape this week.

Frizzle road at 24 Grant Line (our Home)

Doug and Gail

Blog Archive

Countries we have visited