Frizzle road |
Stillwoods Lane.
19 April 2021.
Stonesage, and Reg MacKinnon have
been working on the extension of Stillwoods Lane.
At this time there are two
limitations.
Frizzle road (left) and Stillwoods Lane (Southwards) |
There is an intermittent stream that
crosses lot 5 (phase1). The culvert for this crossing cannot be installed in
the Springtime.
The other limitation is the Spring
Axle Restrictions which limits loads that can be transported. I believe it is
in effect still.
These photos are from today! Just
after a big rainstorm, Saturday and Sunday.
Stillwoods Lane (Northwards) |
They show Stillwoods Lane, work in
progress, and Frizzle road---a temporary access so that the stream is not being
crossed. ‘Frizzle road’ will become a pathway on the completion of Stillwoods
Lane extension.
An update on the surveyors---they
have been in and out. The work is still very incomplete.
Because the survey is incomplete,
there can be no submission to HRM for Final Approval of phase 2.
Hopefully things take shape this
week.
Frizzle road at 24 Grant Line (our Home) |
Doug and Gail